Caldecott Fourth Bore Medallion Design Competition

Above the new Caldecott Fourth Bore, six medallions designed by students in K-12 from Contra Costa and Alameda counties will be cast in concrete. The medallions adorning the entrances of the original two bores were designed in the mid-1930s, and the Caldecott Tunnel and the portals were designated a City of Oakland Keep reading >>

By:
Caldecott Tunnel Progress Update

The latest graphic and numbers are in for the Caldecott Tunnel Fourth Bore!

Eastern portal:

  • 2,426 feet on the east top heading
  • 552 feet on the west top heading
  • 197 feet on the west bench
For more official Caldecott news, visit http://www.caldecott-tunnel.org/ Keep reading >>
By:
Caldecott Tunnel Progress Update

As of October 8, 2011. In standard units, the contractors are 2,385 feet in on the top portion from the east, and 528 feet in on the top portion from the west (almost 90%); and approximately 197 feet in on the bottom portion from the west. That’s a lot of Keep reading >>

By:
Caldecott Tunnel in the News

The Caldecott Tunnel fourth bore is moving along, and grabbing some great media attention along the way!

The New York Times interviewed miners working hard on the tunnel, and used the tunnel as an example of a successful stimulus project, in their piece: Caldecott Tunnel Edges Forward, Tribute to Stimulus Keep reading >>

By:
Caldecott fourth bore project: Happy Anniversary!

What a difference a year makes! The Fourth Bore project has been underway for a year, and make some incredible progress.

On the way, we found fossilssaw some stunning pictures, and learned about the ancient geology of our community. Now, only 109.5 meters remain, and the project Keep reading >>

By:

As of August 13, the Caldecott Tunnel construction is progressing as follows:

  • Topheading eastern portal: 2,080 feet
  • Western portal (topheading): 359 feet
  • Western portal (bench): 77 feet

Source: http://caldecott-tunnel.org/ Keep reading >>

By:
The latest Caldecott Tunnel construction update

 

Just in – new numbers and a new graphic for the Caldecott Tunnel construction:

  • East side topheading: 1705 feet
  • West side topheading: 233.9 feet

With nearly 590 meters tunneled and just over 400 meters left to go, the top heading of the Caldecott Tunnel Fourth Bore is now 60% complete!

Read Keep reading >>

By:
Caldecott Tunnel Progress Update

571.5 meters down, 418.5 meters to go.

The new Caldecott Tunnel is over 57 percent done!

The geological wonders continue. Read about the fossils that Caltrans is digging up in the remaining Sobrante and Claremont sections, or the special precautions crews must take as they dig through the “gaseyKeep reading >>

By:
Pre-historic fossils found in the Caldecott fourth bore project

Of all the people working day and night to drill the fourth bore of the Caldecott tunnel, the coolest job has to be “paleontological mitigation”.

In the last several million years, Contra Costa County has undergone some changes. Several of the excavated fossils are from the Micone era, which lasted Keep reading >>

By:
Did you know the Caldecott Tunnel has gas?

As if tunneling into the East Bay hills wasn’t hard enough, the hint of natural methane in the soil means that crews working on the Caldecott Tunnel can’t use internal combustion engines, cell phones, or even cameras – anything that could make a spark.

These considerations make the Caldecott Tunnel Keep reading >>

By: