Tunneling to begin Monday in Orinda

Caltrans contractors plan to start carving out the fouth bore of the Caldecott Tunnel on Monday. The roadheader that is being used for the project is a 130-ton, 54-foot-long and 14-foot-tall excavation device with a rotating cutter mounted on a boom. The roadheader will dig the 3,389-foot-long bore that will Keep reading >>

By:
Major progress being made at East Portal

The wall shown in the photos below will eventually become the east portal wall. According to Caldecott-tunnel.org, most walls are built from the base upwards.

First, an auger drills large holes, ninety feet deep and several feet apart. Concrete is poured into the circular holes and allowed to harden. Keep reading >>